|
Configuration:
|
Northbound:
|
Southbound:
|
|
Span 1
|
7 I-beams 28/96 x 95 feet
|
8 I-beams 28/96 x 145 feet
|
|
Span 2
|
7 I-beams 28/96 x 95 feet
|
8 I-beams 28/96 x 144 feet
|
|
Span 3
|
7 I-beams 28/96 x 145 feet
|
8 I-beams 28/96 x 144 feet
|
|
Span 4
|
7 I-beams 28/96 x 145 feet
|
8 I-beams 28/96 x 91 feet
|
|
Span 5
|
7 I-beams 28/96 x 145 feet
|
8 I-beams 28/96 x 116 feet
|
|
Span 6
|
7 I-beams 28/96 x 95 feet
|
8 I-beams 28/96 x 116 feet
|
|
Span 7
|
7 I-beams 28/96 x 145 feet
|
8 I-beams 28/96 x 95 feet
|
|
Span 8
|
7 I-beams 28/96 x 145 feet
|
8 I-beams 28/96 x 144 feet
|
|
Span 9
|
7 I-beams 28/96 x 95 feet
|
8 I-beams 28/96 x 91 feet
|
|
Span 10
|
7 I-beams 28/96 x 95 feet
|
8 I-beams 28/96 x 91 feet
|
Prestressed Concrete was the Way to Go
Spanning 1,200 feet across a deep ravine, the Bunker Hill Bridges stretched the
range of prestressed concrete beams and pushed the envelope of constructability
100 feet above the city of Scranton.
With a web of activity below -- the Roaring Brook, a city neighborhood, a concrete
arch bridge, high voltage transmission cables, and an active line of the Pocono
and Northeast Railroad -- 150 prestressed concrete beams were erected under traffic
on Interstate 81. At $48 million, the twin prestressed concrete bridges replaced
two 33-year old steel girder spans that were rapidly approaching the end of their
useful life. The project also increased the capacity on the interstate by adding
shoulder lanes and increased the four lanes to six traffic lanes as part of the
region’s massive Lackawanna Valley Industrial Highway project.
The first challenge was to design a southbound bridge that could be built and put
into service in half-width. This half-width bridge then carried two lanes of northbound
traffic while the old northbound bridge was being replaced. On completion, northbound
traffic was returned to the new northbound bridge and the two lanes of southbound
traffic were also placed on the now wider (three traffic lanes and two shoulders)
northbound bridge. Then the remaining original southbound structure was dismantled.
Pier caps were then modified and the second half-width bridge was connected with
the first half-width southbound bridge and completed. Because of this staged, half-width
construction the southbound structure ended up having an additional line of girders.
The bridges took three years to build. PennDoT’s safety mandate for interstate construction
-- maintain full, two lane capacity on each bridge during replacement -- posed significant
construction and engineering challenges.
One seasoned construction engineer called it "as tough a job as had ever been
done". But in the beginning, the decision to build the Bunker Hill Bridges
using prestressed concrete beams was easy.
The project hit the street designed as a steel I-beam bridge. The prestressed concrete
beam alternate design provided by PennDoT was sketchy at best, conceptual TS&L
(type, size & location) rather than a fully developed set of plans. PennDoT
did, however, allow prospective contractors to bid a contractor alternate design
of their own. This enlightened contracting method, of allowing value engineering
by the contractors as the basis of their bids, won, during 1997, an AASHTO National
Value Engineering Award for the Pennsylvania Department of Transportation and for
the contractor.
At that point, the prestressed concrete industry, under the leadership of Schuylkill
Products, took the lead. Interested bidders were provided complete plans for a prestressed
concrete alternate design that would capitalize on the industry’s ability to deliver
its products quickly and efficiently.
The challenging terrain guaranteed that the bridges would be difficult to build
regardless of whatever design, in the end, won the job. But the site’s constricted
environment gave the prestressed concrete alternate design an opening: Shorter beams
would be somewhat easier to maneuver. As it was, field technicians faced the task
of erecting prestressed concrete beams that were eight feet deep, 91- to 145-feet
long, and weighed between 80 and 104 tons each. Beams were set across nine piers
for each structure. Most would be picked from below by massive, 150 and 220 ton-capacity
cranes squeezed in and around the site’s many natural and man-made obstacles.
"Sometimes the original design...does not take maximum benefit of the material
costs...the site and the circumstances, and how aggressive (the competing industries)
want to be," said Leonard C. Bellanca, PE, senior vice president at G.A. &
F.C. Wagman, Inc., eventual low bidder on the project. "In this case, steel
delivered and erected cost a lot more than prestressed (concrete beams) delivered
and erected."
Through this window of opportunity, prestressed concrete demonstrated its economies
of fabrication: lower labor costs, readily available and cheaper raw materials (cement,
sand and stone, and reinforcing steel) and none of the extra costs required for
steel beam fabrication -- welding, testing, x-raying, sandblasting and painting.
Wagman’s estimators did the math and found more than one million reasons to embrace
the prestressed concrete industry’s alternate design. At the bid opening, the York-based
contractor’s $48.8 million estimate was $3.6 million less than the closest steel
bridge bid. In spite of the additional design and review fees, the need for four
additional piers, and higher field labor costs, prestressed concrete won the race
to the bottom line.
"When you add it all up, and we did this very dispassionately, the delivered
beam cost for prestressed concrete was significantly less," Bellanca said.
"Obviously, prestressed concrete was the way to go."
|